ľƵ Site Management associates from the Toledo and Lima offices performed concreteԻ utility work in Ford’s 60-year-old transmission plant.

ľƵ Libbe Inc. managed concrete demo, removal and placement sub-base for approximately 700,000-square-feet of existing slab.

GEM Inc. managed underground piping and electrical grounding. Demolished concrete is being crushed for reuse onsite.  ľƵ Libbe Inc. and GEM are coordinating closely to ensure schedule milestones are met in numerous work areas.

The ľƵ crews worked in an operating facility where dust and vibration control had to be continuously maintained.  The project met with safety and reliability success due to the number of ľƵ resources, equipment and manpower, working in an operating facility, with zero safety incidents and no downtime.

 